What was the core OBSTACLE in undertaking the activity? Cross-Border train traffic is in a vacuum. In principle it should be left to private companies and the market to establish a cross border infrastructure. But as there is no funding for cross border trains there is little cross border infrastructure. Since most national train traffic is government funded the question then arises: which government will pay and how much?
Which were the main CAUSES of the OBSTACLE? Lack of funding has always been a problem.
Which were the main EFFECTS of the OBSTACLE? That there are no cross border trains, which is an environmental and social problem
Please, describe briefly the factor(s) which mostly (3-4) aggravated the persistence of the Obstacle
Institution Ministerie van Infrastructuur en Milieu
Contact details Dirk Dekkers
………………………………………………………………
Directie Openbaar Vervoer en Spoor
Ministerie van Infrastructuur en Milieu
Plesmanweg 1-6 | 2597 JG | Den Haag
Postbus 20901 | 2500 EX | Den Haag
………………………………………………………………
T 06 525 967 86
F 070 351 65 91dirk.dekkers@minienm.nl
http://www.rijksoverheid.nl/ministeries/ienm
Year of record 2012